RSEB – Auxiliary Crusher House System
Kota, Rajasthan

RSEB – Auxiliary Crusher House System  <br> Kota, Rajasthan

RSEB – Auxiliary Crusher House System
Kota, Rajasthan

Percentage of ZECPL in the Project 100%
LOA/Order Date/ Date of Start of the Project 20.02.1993
Value of contract as per Agreement/ LOA 3.18
Employer's Contact (Address,Tel, Fax) Rajasthan State Electricity Board
Present Status March, 1995
State, in which project is executed Rajasthan

Design, Supply, Erection, Testing and Commissioning including Civil, Structural & Electrical work of Auxiliary Crusher House system, crushing, conveying and screening system of Kota Thermal Power Project, Stage-II (2×210 MW)

×