RRVUNL – Coal Handling Plant Package-B
Suratgarh, Rajasthan

RRVUNL – Coal Handling Plant Package-B  <br> Suratgarh, Rajasthan

RRVUNL – Coal Handling Plant Package-B
Suratgarh, Rajasthan

Percentage of ZECPL in the Project 100%
LOA/Order Date/ Date of Start of the Project 22.11.2000
Value of contract as per Agreement/ LOA 11.13
Employer's Contact (Address,Tel, Fax) Rajasthan Rajya Vidyut Utpadan Nigam Limited, Vidyut Bhawan, Jyoti Nagar, Jaipur
Present Status April, 2007
State, in which project is executed Rajasthan

Design, Supply, Fabrication, Erection, Testing and Commissioning including Civil, Structural, Electrical & Mechanical works for above Coal Handling Plant Package-B for Suratgarh Thermal Power Station, Stage-II (2x250MW)

×