MAHAGENCO – Large Diameter Piping & Steel Tanks
New Parli TPS, Maharashtra
Percentage of ZECPL in the Project | 100% |
---|---|
LOA/Order Date/ Date of Start of the Project | 05.07.2005 |
Value of contract as per Agreement/ LOA | 13.82 |
Employer's Contact (Address,Tel, Fax) | Maharashtra State Power Generation Co. Ltd. |
Present Status | October, 20009 |
State, in which project is executed | Maharashtra |
Design, Engineering, Manufacturing, Assembly, Testing at works, Supply, Erection, Testing & Commissioning of Large Diameter Piping & Steel Tanks with all accessories, auxiliaries along with supply of mandatory spares including civil works for New Parli TPS Project Unit No. 2 (1×250 MW)