KSK MRPL – Fuel Handling System
Gurha, Rajasthan
Percentage of ZECPL in the Project | 100% |
---|---|
LOA/Order Date/ Date of Start of the Project | 04.03.2009 |
Value of contract as per Agreement/ LOA | 12.56 |
Employer's Contact (Address,Tel, Fax) | KSK Mineral Resources Pvt. Ltd. |
Present Status | July, 2012 |
State, in which project is executed | Rajasthan |
Design, Engineering, Supply, Erection, Testing and Commissioning of Fuel Handling System at Mines area for 1×135 MW Lignite based Thermal Power Plant at Gurha, Bikaner